Hy,
just a little question :
is there a way to schedule the following jobs:
job A is waiting for time
job B should be schedule on a futur odat
job C wait for job A and wait for job B if job B is plan
note : job A and job B have different ODAT (odat and odat +1)
regards,
Philmalmaison
just a little question :
is there a way to schedule the following jobs:
job A is waiting for time
job B should be schedule on a futur odat
job C wait for job A and wait for job B if job B is plan
note : job A and job B have different ODAT (odat and odat +1)
regards,
Philmalmaison
It seems, that the job C depends on scheduling of B on next day? isn't it? So i would look this way, because dependency on job A is simple.
If i understand, job B is scheduled on DAY1 with odate of DAY1+1?
You also can schedule make job B to be ordered day before to wait for correct ODATE (i'm sure you know how to ).
So:
1) create a jobX to schedule a jobB with ODAT+1 (with wait for date)
2) in jobX define ON STMNT which will check, if the jobB was successfuly ordered (from sysout, from RC of jobX) and if it is, do "Order/Force JobC"
You have to try, which return codes ctmorder is returning and how the structure of sysout. My suggestion stays on this. I do not have time to play around with it.
If i understand, job B is scheduled on DAY1 with odate of DAY1+1?
You also can schedule make job B to be ordered day before to wait for correct ODATE (i'm sure you know how to ).
So:
1) create a jobX to schedule a jobB with ODAT+1 (with wait for date)
2) in jobX define ON STMNT which will check, if the jobB was successfuly ordered (from sysout, from RC of jobX) and if it is, do "Order/Force JobC"
You have to try, which return codes ctmorder is returning and how the structure of sysout. My suggestion stays on this. I do not have time to play around with it.
Hi,
in this case we are using Group-Scheduling with different options:
1. Way:
Define Job A and C in one "normal" table, B as a group schedule table.
The group schedule table gives the OUT-Cond for Job C not Job B!
Define in the group schedule table a scheduling TAG with the same scheduling criteria as Job A nd Job C, in JOB B the "correct" scheduling criteria.
What happens now:
The scheduling group for JOB B will be planned empty every Day regarding the scheduling criteria and will set the OUT-cond for JOB C. If the scheduling criteria for job B will be arrived, it will also ordered INSIDE OF THE SCHEDULING GROUP and the SCHEDULING GROUP will set the OUT-cond for JOB C, if JOB B ends with OK.
2. Way:
Define all 3 jobs in a group scheduling table and set the ADJUST CONDITION Parameter in the Group Scheduling Table.
We are using Group Scheduling Tables on Z/Os and UNIX with a lot of success.
regards,
schidl
in this case we are using Group-Scheduling with different options:
1. Way:
Define Job A and C in one "normal" table, B as a group schedule table.
The group schedule table gives the OUT-Cond for Job C not Job B!
Define in the group schedule table a scheduling TAG with the same scheduling criteria as Job A nd Job C, in JOB B the "correct" scheduling criteria.
What happens now:
The scheduling group for JOB B will be planned empty every Day regarding the scheduling criteria and will set the OUT-cond for JOB C. If the scheduling criteria for job B will be arrived, it will also ordered INSIDE OF THE SCHEDULING GROUP and the SCHEDULING GROUP will set the OUT-cond for JOB C, if JOB B ends with OK.
2. Way:
Define all 3 jobs in a group scheduling table and set the ADJUST CONDITION Parameter in the Group Scheduling Table.
We are using Group Scheduling Tables on Z/Os and UNIX with a lot of success.
regards,
schidl
Shidl,
but your sollution is, if jobB is to be run on the same day as jobC has to. But jobC (as i understand) is to be submited a day before jobB and only if jobB will be ordered. So in your sollution, jobB is still waiting in group and group does not send condition to C - only after jobB ends (and this is on next day).
If i correctly understand the problem of phillmaison. (and your sollution)
but your sollution is, if jobB is to be run on the same day as jobC has to. But jobC (as i understand) is to be submited a day before jobB and only if jobB will be ordered. So in your sollution, jobB is still waiting in group and group does not send condition to C - only after jobB ends (and this is on next day).
If i correctly understand the problem of phillmaison. (and your sollution)
- richardoku
- Nouveau
- Posts: 20
- Joined: 11 Mar 2008 12:00
Hi All,
to my opinion both hipikll's & schidl's solutions will work. My favourite is to get everything in one Group Scheduling table (schidl's 2.way option).
To clarify:
build one group schedule with the 3 jobs, use 'Adjust condition' on Group level, define tags with the desired schedule criteria. Then create the dependencies; job A to job B and job A to job C (hipikll's concern) then from job B to job C.
Suppose job A and C are planned from Monday thru Thursday and job B is planned from Tuesday thru Friday (one day later) then Control-M will ensure that Job C is not going to wait for Job B (when Job B is not on AJF, e.g. on Monday). If Job B is on AJF then Job C will wait for that Job B to complete (Tuesday thru Thursday). If only Job B is on AJF (on Friday) this is the only job that will be executed.
What about this suggestion? (got a 6.3.01 'deftable' XML-file available on request)
Best regards
to my opinion both hipikll's & schidl's solutions will work. My favourite is to get everything in one Group Scheduling table (schidl's 2.way option).
To clarify:
build one group schedule with the 3 jobs, use 'Adjust condition' on Group level, define tags with the desired schedule criteria. Then create the dependencies; job A to job B and job A to job C (hipikll's concern) then from job B to job C.
Suppose job A and C are planned from Monday thru Thursday and job B is planned from Tuesday thru Friday (one day later) then Control-M will ensure that Job C is not going to wait for Job B (when Job B is not on AJF, e.g. on Monday). If Job B is on AJF then Job C will wait for that Job B to complete (Tuesday thru Thursday). If only Job B is on AJF (on Friday) this is the only job that will be executed.
What about this suggestion? (got a 6.3.01 'deftable' XML-file available on request)
Best regards
- philmalmaison
- Nouveau
- Posts: 1148
- Joined: 08 Jun 2007 12:00
- Location: Ile de France
Job a,b,c
So some additional questions.
one is to create a schedule group, two is to create the tree jobs in the schedule group, schedule group with the ADJUST CONDITION set to YES.
ok but what should be the schedule criteria of the scheduling group
I know for the jobs, so does the criteria inside scheduling group have to be set with all days ?
for ex:
job a = monday to thursday
job b = friday
job c = monday to thursday
what should be the schedule criteria of the scheduling group
regards
Philmalmaison
one is to create a schedule group, two is to create the tree jobs in the schedule group, schedule group with the ADJUST CONDITION set to YES.
ok but what should be the schedule criteria of the scheduling group
I know for the jobs, so does the criteria inside scheduling group have to be set with all days ?
for ex:
job a = monday to thursday
job b = friday
job c = monday to thursday
what should be the schedule criteria of the scheduling group
regards
Philmalmaison
- richardoku
- Nouveau
- Posts: 20
- Joined: 11 Mar 2008 12:00
Hi Philmalmaison,
There will be various possibilities. This is just one of them:
At the Schedule Group definition create one tag 'mon-thu', select 'All' Month Days AND Week Days 'mon' thru 'thu' & select Months All.
Create another tag 'friday', select 'All' Month Days AND Week Days 'fri' & select Months All (jan thru dec).
Next step is to create the jobs A, B & C. It is ok to leave their Schedule Criteria blanco. Just set 'Tag Relationship' to 'Or'. Then press the 'Select Tags' button to include tag 'mon-thu' for Job A & C. Job B will be included with tag 'friday' only.
This should do the trick.
Any questions let me know.
Greetings!
There will be various possibilities. This is just one of them:
At the Schedule Group definition create one tag 'mon-thu', select 'All' Month Days AND Week Days 'mon' thru 'thu' & select Months All.
Create another tag 'friday', select 'All' Month Days AND Week Days 'fri' & select Months All (jan thru dec).
Next step is to create the jobs A, B & C. It is ok to leave their Schedule Criteria blanco. Just set 'Tag Relationship' to 'Or'. Then press the 'Select Tags' button to include tag 'mon-thu' for Job A & C. Job B will be included with tag 'friday' only.
This should do the trick.
Any questions let me know.
Greetings!
- philmalmaison
- Nouveau
- Posts: 1148
- Joined: 08 Jun 2007 12:00
- Location: Ile de France
- philmalmaison
- Nouveau
- Posts: 1148
- Joined: 08 Jun 2007 12:00
- Location: Ile de France
- philmalmaison
- Nouveau
- Posts: 1148
- Joined: 08 Jun 2007 12:00
- Location: Ile de France