I have JobA and JobB.JobB is dependent on JobA's success.Runs through MON to SAT
We have NDP defined at +0000 hrs.
Job A starts at 2330 and can finish before 0000 hrs or may contnue to run beyond 0000 hrs.
when out Condition(ODAT) of JobA is In condition to JobB and when JobA finishes within that day(i.e by 0000 hrs),JobB runs fines.
However,when JobA continues to run after NDP(i.e at +0000),JobB doesnot get kicked off when JobA ends sometime after 0000 hrs.
I tried to use STAT condition but not working as expected.
Please suggest who to create dependency on JObA and JobB so that when ever JobA finishes,JobB has to run