Scheduling job first tuesday of month

All questions about Control-M jobs definitions
Post Reply
User avatar
fredo
Nouveau
Nouveau
Posts: 1
Joined: 20 Aug 2008 12:00

Scheduling job first tuesday of month

Post by fredo » 20 Aug 2008 2:13

Hi,

How can I schedule a Job to start on first tuesday of each month without calendar.

User avatar
ranger67
Nouveau
Nouveau
Posts: 52
Joined: 03 Jan 2008 12:00

Post by ranger67 » 20 Aug 2008 2:34

Days field = 1,2,3,4,5,6,7

Boolean = And

Weekdays field = 2

User avatar
Derick
Nouveau
Nouveau
Posts: 26
Joined: 22 Jun 2007 12:00

Post by Derick » 22 Aug 2008 12:18

Hi,

You can also use D2W1 in the Week Days – Scheduling tab.

Where your start day of the week is Monday, D2 is Tuesday and W1 is week 1.

You can double check your scheduling parameters with Forecast.

:D