DoForceJob outside smart table

All questions about Control-M jobs definitions
Post Reply
ladsvieira
Nouveau
Nouveau
Posts: 1
Joined: 22 Feb 2015 4:59

DoForceJob outside smart table

Post by ladsvieira » 22 Feb 2015 5:08

Hi,

I have several jobs that were working fine on version 6 but now on version 8 has a strange behaviour.
So on V8 several jobs with DoForceJob they force the jobs to be ordered but the jobs are ordered under the application/sub application folder but not under the smart table.

So I have
Application: APP
Sub Application: DW
Smart Table: ALL Jobs

Inside of ALL Jobs I have several jobs and when 1 of those jobs force order another job that is under ALL Jobs table the job is ordered but is ordered outside of ALL Jobs. The job is ordered but stays under the APP/DW.

Anyone has the same problem? Or I am doing something wrong?

Thanks in advance.

Post Reply