Hi

I have 3 jobs like A,B,C. If A job completes it will give the condition to B and C. I don't want B job run after completion of A job. The B job should wait for 4 hrs after A job completion.

Please help

Thanks

User avatar
Danny
Nouveau
Nouveau
Posts: 21
Joined: 18 May 2010 12:00
Location: EMEA
Contact:

Post by Danny » 10 May 2012 1:15

Hi, I don't know what the job B is like, but if it is a script or a command, you could use the sleep command.