Stop job ciclyc in executing
Posted: 27 May 2011 12:33
Hi to all.
I have a problem and not how to solve it.
I have a cyclic job that lasts about 30 minutes. Make an FTP to an external server, and sometimes stands in the ftp, and the job does not end in CONTROL-M.
I have an alert that tells me if the job is running over 45 min. So I see that has been caught.
But when it is not working time is a problem because no one detects that it has been caught and is a critical job.
As I can stop the execution of the job and then re-executed without the intervention of a person.
There any way to Control-M make a kill when the exectime exceeds 45 min.
There are nights that gets caught all night long.
Thank you very much to all.
I have a problem and not how to solve it.
I have a cyclic job that lasts about 30 minutes. Make an FTP to an external server, and sometimes stands in the ftp, and the job does not end in CONTROL-M.
I have an alert that tells me if the job is running over 45 min. So I see that has been caught.
But when it is not working time is a problem because no one detects that it has been caught and is a critical job.
As I can stop the execution of the job and then re-executed without the intervention of a person.
There any way to Control-M make a kill when the exectime exceeds 45 min.
There are nights that gets caught all night long.
Thank you very much to all.