Job running long with incomplete output

Post by kayenath » 09 Aug 2010 9:08

The job is overrunning and getting completed with the incomplete output.

Details: The script which is being executed by job is running a command and getting the output on the unix server (same server where the script is placed)and again doing a remote execution on the other server,getting the output and appending on to the existing output on the server.
when the script is run on the server it is getting executed within no time giving complete output but when the same script is scheduled to run by job it is taking a very long time with incomplete output. Giving only half of the output and the other half output of doing remote execution and appending the output to the existing output is not happening.