When running a process chain type SAP job upon failure the job is a cyclic job so it starts over however it errors out everytime the job run that same day. failed due to an SAP error over the weekend. This job has not been running correctly since this failure (this happens every time this job fails once and then will fail on every run thereafter until the next day’s schedule is started)
It seems that the Log Id for every run (3 so far today) has the same Log ID. BMC is emailing an error every hour, yet SAP is never actually called to execute the job. We need BMC to generate a new Log Id for each run (each hour).
This is for Control M 6.2.01. SAP process chain issue
Thanks
TRAVO
SAP Log ID - Process Chain
SAP Log ID - Process Chain
The problem is once the job restarts it contiues to fail every times there after. Even after the problem has been corrected. The error is with the chain log Id not changing. It remains the same. It seems that the Log Id for every run has the same Log ID.
BMC is emailing an error every hour, yet SAP is never actually called to execute the job. We need BMC to generate a new Log Id for each run (each hour).
BMC is emailing an error every hour, yet SAP is never actually called to execute the job. We need BMC to generate a new Log Id for each run (each hour).
SAP Log ID - Process Chain
Great thanks I understand that process, I'll try that.
Thanks again.
TRAVO
Thanks again.
TRAVO