Post by Ozarm » 02 Sep 2010 6:08

Hi,

I have a question about multiagent operation.

for example
I have a job define with mutli agent option

1 )the table I've 3 batchs associated to the same NODEGRP XXX
2 )I've many nodeid associated to the NODEGRP XXX for example 6 nodeid

During the NewDayProcedure, many jobs well ordered
except few jobs which ordered double.

Why this mechanism?
Somebody was already confronted has it?
Not log indicating a dysfunction

Thx's for your answer

LordOfAfford

Post by LordOfAfford » 03 Sep 2010 8:17

Hi,

Don't put NODEGRP XXX in the table, just put it at job level and then the doubles should disappear.
There is very little that needs to be defined on table level, and i certainly think NODEGRP XXX is not 1 of them.

User avatar
philmalmaison
Nouveau
Nouveau
Posts: 1148
Joined: 08 Jun 2007 12:00
Location: Ile de France

Post by philmalmaison » 14 Sep 2010 11:26

some jobs have been defined with "run in all nodes in the group", others are not...

regards
Philmalmaison

User avatar
Ozarm
Nouveau
Nouveau
Posts: 37
Joined: 14 Jun 2007 12:00

Post by Ozarm » 14 Sep 2010 2:43

hi,

thx's for tips
We used Control-M with scheduling job and not scheduling table.
all Nodegrp & nodeid OK

All jobs ordered normally now ... so i suppose maybe many ordered by specific request ... arff