Hi All,
I have a query on SNA_UDLY.
There is a command based job created with the name as SNA_UDLY and its command is "ctmudly -DAILY_NAME %%JOBNAME -odate_option run_date".
And this job is applied for all the jobs which runs on weekday and weekends.but for weekends jobs calender has created to run on every friday, with maxwait as 3,but all the weekends jobs are loading only on saturdays only, not on fridays.
I guess i need to understand the below command
ctmudly -DAILY_NAME %%JOBNAME -odate_option run_date.
Could anyone explain about this ...
SNA_UDLY job
Why use the ctmudly command for this type of problems?
Use the scheduling tab also with jobs in scheduling (/smart) tables with different calendars and schedulation if the scheduling problem is more complex.
So you can use the forecast to control and simulate the schedulations, be sure to results, etc.
Regards
Use the scheduling tab also with jobs in scheduling (/smart) tables with different calendars and schedulation if the scheduling problem is more complex.
So you can use the forecast to control and simulate the schedulations, be sure to results, etc.
Regards
Thanks soo much chookgate and mauriziog.
Chookgate: i understood the concept of the command by now,this perfectly applicables to the weekday jobs which has ESt time zone but the default is GMT, in this case jobs are getting ordered and waiting for the EST time to run where-ever its has defined.
But all weekend jobs are defined in default timezone(i.e GMT) still i could not understand, its loading only on saturday and sunday only, even its schedule criteria is set to run only on friday (defined in the calender)
Chookgate: i understood the concept of the command by now,this perfectly applicables to the weekday jobs which has ESt time zone but the default is GMT, in this case jobs are getting ordered and waiting for the EST time to run where-ever its has defined.
But all weekend jobs are defined in default timezone(i.e GMT) still i could not understand, its loading only on saturday and sunday only, even its schedule criteria is set to run only on friday (defined in the calender)