Control Resource

Post by Gopikkd » 20 Aug 2012 4:18

Could you explain about Control Resource in Control-M. What is the difference between Quantitative Resource and Control Resource.?

User avatar
siipryasa
Nouveau
Nouveau
Posts: 11
Joined: 18 May 2008 12:00
Location: Mexico, D. F.

REsources

Post by siipryasa » 20 Aug 2012 6:07

Hi,

The resource quantitives are resource with quantitive for example tapes defined with valor 10, when a job or task need a tape, define in the scheduler tape and quantitive one.

The resource of control onnly has two valor EXCLUSIVE or SHARE,

If you has many task or job's and need what the process is execute only one by one used the resource for example ORACLE with valor E to all the task's and only a job will go to execute. If you need mass job's or task used the resource with valor Share and many task or job's will go to execute for example resource of CONTROL DISCO with valor S to all job's or task into define.
Best Regards