Search found 807 matches

by mauriziog
07 Dec 2012 10:15
Forum: Control-M Enterprise Manager
Topic: How to get access to CONTROL-M/EM OR SERVER CMDLINE
Replies: 3
Views: 4576

You have installed on windows 7.0 the client components and the servers components are on other machine? Or you have installed all in windows 7.0 machine ? If you have all server components installed on one machine you have also configured them ? Which access you need in this case? In windows you ca...
by mauriziog
06 Dec 2012 9:31
Forum: Control-M Enterprise Manager
Topic: User Daily is erased in the New Day if Resources is removed
Replies: 2
Views: 4789

The userdaily remains if you update jobs resource definition, etc. In some way you have done write and upload removing the SYSTEM or you have put the SYSTEM but not "uploaded" the table. If you have forecast, to control that all is ok, use the "load forecast"; so you can control that tables are orde...
by mauriziog
05 Dec 2012 8:17
Forum: Control-M Server
Topic: Statistics Parm Change Refresh
Replies: 1
Views: 8348

Yes, is a parameter write in the config.dat so you must recycle the control-M server component (stop and up). When you stop the server the gateway disconnect and then, when the server is up, gateway reconnect and download (refresh in em gui needed). You have a time during the stop and restart that y...
by mauriziog
04 Dec 2012 1:56
Forum: Exploitation / Operation
Topic: Using LDAP With Control-M EM 7.0
Replies: 2
Views: 5125

Be sure to have followed the steps reported in documentation: Control-M Administration Guide pag. 171 (in version 7.0) See the section about user\groups definition. In particular can be that you cant find the user in the LDAP tree, the Active Directory is a little different, but in general often you...
by mauriziog
03 Dec 2012 6:28
Forum: Exploitation / Operation
Topic: Separate Date and time Feld from Query on Control-M
Replies: 5
Views: 9672

For the date, if you use the active jobs report you can create a template that extract not the current AJF but the previous day. Then you schedule the report at the first day of the month. For dates formats, you can define a macro in the excel sheet, so that can be executed when the sheet is opened:...
by mauriziog
03 Dec 2012 6:11
Forum: Exploitation / Operation
Topic: Separate Date and time Feld from Query on Control-M
Replies: 5
Views: 9672

For this kind of report why you dont use the Reporting Facility ?
:D

But you are true: the problem of the start time/end time format remain. You can export the report on xls files and in excel filtering the column values showing only time ?

Regards
by mauriziog
03 Dec 2012 3:28
Forum: General News
Topic: ANNOUNCEMENT: VERSION 8.0 RELEASED 23 Nov 2012
Replies: 5
Views: 15754

I think that is better wait untill end of genuary 2013, is a very new version.

(I've migrated to a version 7.0 last week too)

Regards
by mauriziog
03 Dec 2012 9:33
Forum: Monitoring
Topic: System Date for first and last day of the month
Replies: 3
Views: 11667

Yere one solution in the date format YYYYmmDD: in set panel: data1=%%$CALCDATE %%$OYEAR.%%OMONTH.01 +32 data2=%%$CALCDATE %%$OYEAR.%%OMONTH.01 +62 sub1=%%SUBSTR %%data1 1 6 sub2=%%SUBSTR %%data2 1 6 LastDay =%%$CALCDATE %%sub2.01 -1 FirstDay =%%sub1.01 The echo of variables calculated as above (job ...
by mauriziog
29 Nov 2012 9:44
Forum: Monitoring
Topic: System Date for first and last day of the month
Replies: 3
Views: 11667

Yes you can do that, is a usual need. You may use the %%CALCDATE function and the %%SUBSTR function. The calculation are based on the %%ODATE or %%$ODATE variable. I write here the sintax of functions, so you can try to solve the problem; then we can compare the solutions: ok ? Calcdate result=%%CAL...
by mauriziog
28 Nov 2012 10:19
Forum: Monitoring
Topic: Automatic email if job has not started, is late.
Replies: 4
Views: 8718

You can:
1. send all alerts to a script and here send a mail
2. shout directly to a program that send a mail

In both cases you have to build a program/script that reside on the:
1. controlM EM server
2. controlM server

Witch SO you have on the server components?

Regards
by mauriziog
28 Nov 2012 10:15
Forum: Control-M Enterprise Manager
Topic: Step tab code value
Replies: 5
Views: 6795

In code you read the output(=SYSOUT), you cant use the sintax you have put here.
The other manner is to sent to the scritp the time value and in the script writing some message string that in the step you can capture and set the variable.

Regards
by mauriziog
28 Nov 2012 12:24
Forum: Control-M Enterprise Manager
Topic: Step tab code value
Replies: 5
Views: 6795

For your problem use more than one job definition, each with a specific parameter value.

Regards
by mauriziog
28 Nov 2012 12:22
Forum: General News
Topic: ANNOUNCEMENT: VERSION 8.0 RELEASED 23 Nov 2012
Replies: 5
Views: 15754

Its a official 8.0 version, not a trial version.

Is only ... young! :)
by mauriziog
25 Nov 2012 9:43
Forum: General News
Topic: ANNOUNCEMENT: VERSION 8.0 RELEASED 23 Nov 2012
Replies: 5
Views: 15754

ANNOUNCEMENT: VERSION 8.0 RELEASED 23 Nov 2012

Version 8.0 finally released !
:D :) :D
by mauriziog
21 Nov 2012 12:42
Forum: Control-M Server
Topic: Communication error with database
Replies: 2
Views: 5023

Error in upload can be on job definition: check the changes made.

The logs path are:
EM:
InstallHome /Log

ServerCTM:
InstallHome Ctm_server/Proclog

Agent:
InstallHome Default/PROCLOG

If you have many agents or the agent is in cluster substitute "Default" with the "AgentName".

Regards