Re: Conditions dependency

Try putting Out condition in Job A in Steps tab. No dependency line between them.. But still A will trigger B
by vamsikumar
30 Oct 2015 8:01
Forum: Job Definition
Topic: Cyclic interval change
Replies: 0
Views: 88555

Cyclic interval change

Hello,

Is there any option to change the cyclic interval change incase of failure or success in Control M Version 7.

For example: We scheduled a job to run every 3 hours. Incase if it fails, it should run every 5 minutes until in completes successfully.
by vamsikumar
18 Mar 2014 7:35
Forum: Job Definition
Topic: Email alert on third failure
Replies: 8
Views: 7775

Hello,

In this case, we will get an email even the 3rd is successful. we need if 3rd run failed, then only we need email.

If 3rd run is success, no email or any other actions required.

Thanks in advance!!
by vamsikumar
17 Mar 2014 8:57
Forum: Job Definition
Topic: Email alert on third failure
Replies: 8
Views: 7775

Email alert on third failure

Hello All, i have one requirement. kindly some one please help. we have one job which is scheduled to run daily. If the job failed for 1st time, it should rerun. Again for 2nd time fails, again it should rerun. If the job third time fails, then, need an email to group of people. Kindly advise me how...
by vamsikumar
10 Dec 2013 9:18
Forum: Job Definition
Topic: send email when the job is running longer
Replies: 4
Views: 4208

You can set an email alert in PostProc tab if job running more than some defined time. [Ex: Running more than 120 minutes]
by vamsikumar
13 Nov 2013 4:50
Forum: Job Definition
Topic: Email alert in steps tab.
Replies: 2
Views: 2757

In the below log, 1st time email alert failed. 2nd time, it was successful. Any idea where the issue is. 11/13/2013 3:20:09 AM SL5105 SUBMITTED TO ******** 11/13/2013 3:20:10 AM TR5101 STARTED AT 20131113032009 ON ******** 11/13/2013 3:20:10 AM TR5120 JOB STATE CHANGED TO Executing 11/13/2013 3:20:1...
by vamsikumar
08 Nov 2013 3:59
Forum: Job Definition
Topic: Email alert in steps tab.
Replies: 2
Views: 2757

Email alert in steps tab.

Hello All,

I have set an email alert in steps tab. 1st time job ended OK (just command line sleep 5). but email alert failed. Just reran the job, then the email alert was successful. Any idea where the issue is.
by vamsikumar
08 Nov 2013 2:00
Forum: Job Definition
Topic: cyclic jobs A , B ,C to run in order
Replies: 10
Views: 7364

I think, Dummy job is not required in this scenario.

We can keep the condition directly to job A what we are supposed to put the Dummy job.
by vamsikumar
12 Sep 2013 7:59
Forum: Control-M Server
Topic: Table Name for Table details
Replies: 3
Views: 7193

Thanks everyone for your responses.

But I was not able to find the above mentioned table in my database.

After my analysis, I got the table name and Finally used below query.

select SCHEDTAB, DAILYNAME from CMS_SCHEDT;

Thanks!!!
by vamsikumar
03 Sep 2013 7:17
Forum: Control-M Server
Topic: Table Name for Table details
Replies: 3
Views: 7193

Table Name for Table details

Hi All,

Can someone help me by providing the table name in database which contains details of all control M tables which exists in desktop with respective user daily.

Thanks in Advance!
Vamsi Kumar