Hi GrandSteph You Could use the MAYBE (#-)Condition. JOB A will always require JOB C to run and complete, but will only need JOB B Condition if it has been ordered In JOB A add the following IN Conditions JOBC-TO-JOBA #-JOBB-TO-JOBA In JOB B add #-JOBB-TO-JOBA as an OUT Condition This should then wo...
- 10 Jan 2012 4:57
- Forum: Job Definition
- Topic: Issue when defining In Conditions
- Replies: 7
- Views: 5847
Hi yohcha You Could use the MAYBE (#-)Condition. JOBD will always require JOB A to run and complete, but will only need JOB B and JOB C Conditions if they have been ordered In JOB D add the following IN Conditions JOBA-TO-JOBD #-JOBB-TO-JOBD #-JOBC-TO-JOBD In JOB A add JOBA-TO-JOBD as an OUT Conditi...
- 09 Nov 2011 1:53
- Forum: Control-M Server
- Topic: Control-M Server migration from 6.4 to 7
- Replies: 1
- Views: 3072
Control-M Server migration from 6.4 to 7
Has anybody experienced any problems with the Migration Toolkit for the above migration. I have been told that there are issues with the EM Database not being updated correctly and there may be missing QR's, Conditions etc
Thanks
Thanks
- 19 May 2011 11:26
- Forum: Exploitation / Operation
- Topic: limit number of jobs that order onto the AJF
- Replies: 1
- Views: 2411
limit number of jobs that order onto the AJF
is there a way to limit the number of jobs that is ordered onto the AJF on a daily basis
This is on windows server
This is on windows server
- 24 Mar 2010 11:19
- Forum: Control-M Control Module
- Topic: CONTROL-M/CM for AFT **Information Needed**
- Replies: 2
- Views: 3626
CONTROL-M/CM for AFT **Information Needed**
Hi
Does anybody know if CONTROL-M/CM for AFT can be used for a Fujitsu Server running VME
Regards
Does anybody know if CONTROL-M/CM for AFT can be used for a Fujitsu Server running VME
Regards
- 24 Mar 2010 11:17
- Forum: Batch Impact Manager
- Topic: CONTROL-M/CM for AFT ***Urgent Info Needed***
- Replies: 1
- Views: 6012
CONTROL-M/CM for AFT ***Urgent Info Needed***
Hi
Does anybody know if CONTROL-M/CM for AFT can be used for a Fujitsu Server running VME
Regards
Does anybody know if CONTROL-M/CM for AFT can be used for a Fujitsu Server running VME
Regards
- 14 Oct 2009 8:30
- Forum: Control-M Control Module
- Topic: Job’s Odate is later than the CONTROL-M working date - NOT!!
- Replies: 3
- Views: 8260
Hi All the Jobs that needs EST Timezone set , and the CTM Server is on EST. This worked fine until the weekend When the new Day procedure is run at 07:00 it orders the jobs for the next day. When that date starts the jobs that supposed to , don't submit and say "Job’s Odate is later than the CONTROL...
- 13 Oct 2009 10:38
- Forum: Control-M Control Module
- Topic: Job’s Odate is later than the CONTROL-M working date - NOT!!
- Replies: 3
- Views: 8260
Job’s Odate is later than the CONTROL-M working date - NOT!!
Jobs are Ordered by New Day Procedure OK and remain in the Active Jobs File (AJF) waiting in "Wait Odate" State. Even though the ODAT has been reached Message = Job’s Odate is later than the CONTROL-M working date for the relevant timezone. Job will wait for the relevant day to begin All jobs are se...
- 19 Aug 2009 11:51
- Forum: Control-M Control Module
- Topic: Urgent help Needed for Peoplesoft CM Owner Setup
- Replies: 0
- Views: 10641
Urgent help Needed for Peoplesoft CM Owner Setup
Hi I need help setting up an owner that can submit PS Jobs using the PS8 Tab Currently the Owner is a PS Id that works and can see the database, but when trying to submit job it comes back with not authorised. Is there a Unix profile or anything that can be used to submit the job that takes on all t...
- 18 Aug 2009 4:43
- Forum: Control-M Control Module
- Topic: PeopleSoft Cm for Control M version 6.2.01
- Replies: 2