Search found 50 matches

by catchtony
07 Jan 2011 6:42
Forum: Control-M Enterprise Manager
Topic: How to delete jobs/tables from Control-M EM?
Replies: 3
Views: 9025

Hi,

Do you click on "save as draft" on the job(s) after making the changes in desktop ?

Also you can find all the docs based on your EM version here

http://www.scheduler-usage.com/modules. ... ad&cid=199

Hope this helps and good luck with your training
by catchtony
04 Jan 2011 9:24
Forum: Control-M Server
Topic: Dependency Job unable to get it work as expected
Replies: 2
Views: 2961

why don't you make Job A to force Job B on completion in the steps tab instead of conditions based.
by catchtony
22 Dec 2010 7:15
Forum: Control-M Server
Topic: (in/out conditions)
Replies: 2
Views: 2913

Put the maxwait under execution tab to 3 in both the jobs.
by catchtony
22 Nov 2010 7:37
Forum: Control-M Server
Topic: extra characters in scheduling tab while migrating from 2.24
Replies: 2
Views: 2676

Nobody has any solutions ?
by catchtony
18 Nov 2010 3:57
Forum: Monitoring
Topic: New Day Stats
Replies: 5
Views: 4609

Sadly enough as I do not work on windows :oops: but if the below post would be helpful to get some hints on win server

http://www.scheduler-usage.com/modules. ... highlight=
by catchtony
17 Nov 2010 7:26
Forum: Monitoring
Topic: New Day Stats
Replies: 5
Views: 4609

you may use the following utility : ctmlog list fromdate fromtime todate totime | egrep 'NEW DAY PROCEDURE STARTED|DOWN|CLEANUP|SHOUT TO' where date and time has to be in yyyymmdd & hhmm format you will get the following output :- |1117|0800|00000|CD|5040|NEW DAY PROCEDURE STARTED |1117|0800|00000|C...
by catchtony
16 Nov 2010 4:46
Forum: Control-M Server
Topic: extra characters in scheduling tab while migrating from 2.24
Replies: 2
Views: 2676

In additon to below as we now have to adjust scheduling parameters because of the migration, if we have to move calendar entries from the field "Month Days Calendar" to "Weekdays Calendar" in the scheduling tab of the jobs, is there any easy way despite of manually moving the entries ? Please note t...
by catchtony
15 Nov 2010 4:26
Forum: Job Definition
Topic: ConfCal, this unknown!
Replies: 9
Views: 8291

As far as I understood, you have put the same scheduling of Mon to Sat in job A and job B whereas your timings do matter here as your NDP starts at 11 am everyday. So in your case if any of your job has to run at 8 AM, then in Control-M we call it AM job, for that you have to schedule your job to ru...
by catchtony
15 Nov 2010 3:45
Forum: Control-M Server
Topic: extra characters in scheduling tab while migrating from 2.24
Replies: 2
Views: 2676

extra characters in scheduling tab while migrating from 2.24

Hi, We been facing that our scheduled jobs are introduced with some extra characters in the scheduling tab when we migrate from 2.24 to 6.20 which gravely effects the immediate next Newday when unwanted jobs come into AJF and those jobs which were supposed to come, do not build because of the mess u...
by catchtony
11 Nov 2010 4:20
Forum: Job Definition
Topic: combining a query and command
Replies: 1
Views: 2231

combining a query and command

When we get the request to cancel those jobs which run on xyz node on date xxxx/xx/xx, I run a query and then a command to verify what all jobs need to be cancelled. Query :- select JOBNAME from CMS_JOBDEF where NODEID like <nodeid> Command :- ctmrpln DJ Y <table_name> '*' <Date> and then match for ...
by catchtony
06 Oct 2010 8:23
Forum: Reporting
Topic: Please help me for my request
Replies: 5
Views: 4063

What kind of report you looking for ? what content ? what version of Control-M you using etc etc
by catchtony
04 Oct 2010 11:39
Forum: Job Definition
Topic: Force by job
Replies: 1
Views: 1957

Hello shamit,

Kindly use 3.14 search option to look out for the the forced job :wink: :D
by catchtony
29 Sep 2010 8:17
Forum: Job Definition
Topic: scheduling issue
Replies: 1
Views: 2057

scheduling issue

Hi, If somebody can please help me out with this scheduling :- Suppose I have jobs A, B, C, D, E, F .. now the requirement is such that we have to run 4 jobs at a time only, So if any of the 4 jobs out of A , B, C , D completes it should then trigger E etc. We cannot use quantative resources as it i...
by catchtony
29 Sep 2010 8:09
Forum: Job Definition
Topic: twin file watcher
Replies: 2
Views: 1980

Thanks Woody and it was very informative
by catchtony
27 Sep 2010 8:43
Forum: Job Definition
Topic: twin file watcher
Replies: 2
Views: 1980

twin file watcher

Hi,

If two file watchers are looking for same file in the same path at a time, will both detect the file simultaneously or one will detect it faster than the other ?