 Post subject: Specific Scheduling Job
PostPosted: 01 Jun 2017 2:56 
Offline
Nouveau
Nouveau
User avatar

Joined: 16 Jul 2010 12:00
Posts: 13
Hello,

I try to schedule a job who must run on the 25th of the month except if it's a non work day.
My new day procedure begin at 12am and the job will be executed at 7am (next day after new day procedure)

If the 25 is a sunday, the job must run on friday.
If the 25 is an offday (like 05/25/2017), the job must run the day before.

I've tried:
Month Day 25 AND Week Days ALL Months ALL
Conf Call (Specific Calendar with only work day - off day and saturday/sunday are off) Shift Prev Day by -1

It's almost that I want but there is an issue on December because the job is launched twice (21 and 28)

Thanks in advance for your ideas ;)


Top
   
PostPosted: 22 Jul 2017 9:10 
Offline
Nouveau
Nouveau
User avatar

Joined: 26 Apr 2005 12:00
Posts: 696
Location: PARIS
Hi

The most efficient is to create a regular calendar.


Top
   
Display posts from previous:  Sort by  
Post new topic  Reply to topic  [ 2 posts ] 

All times are UTC+01:00


Who is online

Users browsing this forum: No registered users and 1 guest


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
cron
Powered by phpBB® Forum Software © phpBB Limited
The site created by Franck YOT. Images, logo, content and trademarks about Control-M products are property of BMC Software.
All the comments are property of their posters. Images, logo, content and design are © copyright by Scheduler-Usage.com. All Rights Reserved