Hi,
I need a Job cyclic that execute from 0400 to 2200 hours.
If I have the new procedure day at 07.00.
How could I schedule? If I put 2200 until don't execute. The job does not delete with new procedure day?
Any help?
Many thanks


Top
   
PostPosted: 01 Aug 2014 12:04 
Offline
Nouveau
Nouveau
User avatar

Joined: 26 Apr 2005 12:00
Posts: 696
Location: PARIS
Hi

Look this post


Top
   
PostPosted: 01 Aug 2014 1:04 
Offline
Nouveau
Nouveau
User avatar

Joined: 27 Dec 2006 12:00
Posts: 73
fyot wrote:
Hi

Look this post


Thanks
But I cant solve my problem with these post.

I detail my problem:
I have a job cyclic from 04.00, and the job must execute every 30 minutes. Normally it fails and I search a determinate string to ended OK so by these way don't generate alert.
I have other condition in steps that if ended ok with compstat=0 add other condition to execute the post job.

The problem is that job must execute from 04.00 to 22.00 (as long as the job not ended with compstat=0) and the new procedure day begins at 07.00 so the cyclic job is deleted at 07.00

Do you know some solution that could I apply?
Thanks, sorry for my english!


Top
   
PostPosted: 01 Aug 2014 1:54 
Offline
Nouveau
Nouveau
User avatar

Joined: 26 Apr 2005 12:00
Posts: 696
Location: PARIS
Other way is to have two job identical but up to plan to the day after.

First from 4:00 to 7:00
Second from NDP to 22:00

If job need to wait conditions, use PREV date in job definition.


Top
   
PostPosted: 01 Aug 2014 2:04 
Offline
Nouveau
Nouveau
User avatar

Joined: 27 Dec 2006 12:00
Posts: 73
fyot wrote:
Other way is to have two job identical but up to plan to the day after.

First from 4:00 to 7:00
Second from NDP to 22:00

If job need to wait conditions, use PREV date in job definition.



But.. .if the job finished OK at 0600 and also the post jobs. The jobs identical of the day after should not execute it


Top
   
PostPosted: 01 Aug 2014 2:11 
Offline
Nouveau
Nouveau
User avatar

Joined: 26 Apr 2005 12:00
Posts: 696
Location: PARIS
If job wait a condition, and if you delete condition after execution,
each of will not start if condition doesn't exist.


Top
   
PostPosted: 07 Aug 2014 2:26 
Offline
Nouveau
Nouveau
User avatar

Joined: 19 Jun 2013 12:00
Posts: 36
does your ajf refresh on 0700?


Top
   
PostPosted: 07 Aug 2014 5:00 
Offline
Nouveau
Nouveau
User avatar

Joined: 27 Dec 2006 12:00
Posts: 73
jCarlos wrote:
does your ajf refresh on 0700?

Yes


Top
   
PostPosted: 07 Aug 2014 8:26 
Offline
Nouveau
Nouveau
User avatar

Joined: 26 Apr 2005 12:00
Posts: 696
Location: PARIS
But.. .if the job finished OK at 0600 and also the post jobs. The jobs identical of the day after should not execute it


No, new jobs will have new depencies considering new ODATE.
Jobs defined to be executed after 0700 must have condition with PREV ODATE


Top
   
Display posts from previous:  Sort by  
Post new topic  Reply to topic  [ 9 posts ] 

All times are UTC+02:00


Who is online

Users browsing this forum: No registered users and 3 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Limited
The site created by Franck YOT. Images, logo, content and trademarks about Control-M products are property of BMC Software.
All the comments are property of their posters. Images, logo, content and design are © copyright by Scheduler-Usage.com. All Rights Reserved