 Post subject: Cyclic Job.
PostPosted: 31 May 2013 10:29 
Offline
Nouveau
Nouveau
User avatar

Joined: 03 Sep 2011 12:00
Posts: 7
Are cyclic jobs that run from the start of a previous run queued if the previous run is over the defined cyclic time?

I have a cyclic job which is scheduled to run every 15 minutes from the start of the previous run but sometimes the job runs for 20-30 min. I noticed the difference between some runs after a long run were short. Now, I know the run after 15min will occur immediately the current run is complete.


Top
   
 Post subject:
PostPosted: 03 Jun 2013 8:49 
Offline
Nouveau
Nouveau
User avatar

Joined: 28 Jul 2011 12:00
Posts: 46
hi pone2332,


answer is YES...

If you give rerun every 15 from job start time , it will calculate the time from job submission to finish .

if job run more than 15 min than next run should start immediately after the previous run ..

if you want to make gap of 15 min in each run then give all interval from job END

Regards,
Mani[/img][/url]


Top
   
Display posts from previous:  Sort by  
Post new topic  Reply to topic  [ 2 posts ] 

All times are UTC+02:00


Who is online

Users browsing this forum: No registered users and 3 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
cron
Powered by phpBB® Forum Software © phpBB Limited
The site created by Franck YOT. Images, logo, content and trademarks about Control-M products are property of BMC Software.
All the comments are property of their posters. Images, logo, content and design are © copyright by Scheduler-Usage.com. All Rights Reserved