Hi,


I have a SMART Table that I assigned 2 RBCs. Inside the table, I have 4 jobs named A, B, C and D. Jobs A, B and C have the same calendars while Job D is different. I expect that when I order the job (through ctmorder command or ctmudly) I will only see jobs A,B and C ordered to AJF based on the calendar setting of each job. But what happens is job D is also ordered to the AJF.


When I run Load Forecast against the SMART Table, I can see the result I expect wherein the jobs A, B and C are ordered but not D. Is there anything I am missing on why job D is ordered together with jobs A, B and C despite the differences in the calendar setting for each job? Does the calendar setting of the SMART Table overrides the calendar setting of the job inside the SMART table?


thanks in advance.


rgds,

Noynoy


Top
   
 Post subject:
PostPosted: 07 May 2013 7:50 
Offline
Nouveau
Nouveau
User avatar

Joined: 13 Jun 2007 12:00
Posts: 317
When you ordered the table, did you "order" or "force"? "Order" will follow schedule and skip job D. "Force" will ignore schedule and include all jobs.


Top
   
Display posts from previous:  Sort by  
Post new topic  Reply to topic  [ 2 posts ] 

All times are UTC+01:00


Who is online

Users browsing this forum: No registered users and 1 guest


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Limited
The site created by Franck YOT. Images, logo, content and trademarks about Control-M products are property of BMC Software.
All the comments are property of their posters. Images, logo, content and design are © copyright by Scheduler-Usage.com. All Rights Reserved