PostPosted: 27 Jan 2013 10:53 
Offline
Nouveau
Nouveau
User avatar

Joined: 24 Apr 2008 12:00
Posts: 4
Using Midrange Control-M 6.3, need to schedule a job to run ALLDAYS except the job should not run on the last business day of month. Is there a way to do this without a special calendar?

Thanks,
Jean


Top
   
PostPosted: 28 Jan 2013 6:24 
Offline
Nouveau
Nouveau
User avatar

Joined: 12 May 2011 12:00
Posts: 8
Yes you can schedule it. Using two calendars. One is which runs on all days and the other one is which runs only on business days.
You need to give the business days calendar under Months days and use -L1 in rules and select the OR option. Under [b][b]weekdays mention All days calendar[/b][/b] you will get what you need.


Top
   
 Post subject:
PostPosted: 28 Jan 2013 7:54 
Offline
Nouveau
Nouveau
User avatar

Joined: 24 Apr 2008 12:00
Posts: 4
ashwin080,

Thanks for the quick response!


Top
   
Display posts from previous:  Sort by  
Post new topic  Reply to topic  [ 3 posts ] 

All times are UTC+01:00


Who is online

Users browsing this forum: No registered users and 1 guest


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Limited
The site created by Franck YOT. Images, logo, content and trademarks about Control-M products are property of BMC Software.
All the comments are property of their posters. Images, logo, content and design are © copyright by Scheduler-Usage.com. All Rights Reserved