Author:  Gopikkd [ 27 Jan 2017 7:57 ]
Post subject:  New Day process hung

Hi,

What could the be reason the New day process in hung status and not completed on time.

Thanks,
Gopikkd.

Author:  fyot [ 11 Feb 2017 11:54 ]
Post subject:  Re: New Day process hung

Hi

A lot of reason could create that problem.
One of them, all table are with Automatic Method or SYSTEM userdaily
Create another userdaily alias as ONE, and aplly it to all Tables except on table having a job running folowing command
ctmudly -DIALYNAME ONE

This will reduce time of NDP.