Bonjour,

utilisateur d'un environnement Control-M v6.1.03 sous Unix, je suis ? la recherche d'une m?thode alternative ? l'utilitaire <ctmrpln> pour simuler la charge d'une mise au plan pour une date pr?cise.

Toutes id?es bienvenues

D'avance merci
Cordialement
Walty

**********************************************************

Hello,

user of an Control-M environment v6.1.03 under Unix, I am in the search of an alternative method to the utility <ctmrpln> to simulate the load of a setting in the plan for a precise date.

All welcome ideas
In advance thank you

Cordially
Walty


Top
   
 Post subject:
PostPosted: 04 Dec 2006 11:29 
Offline
Nouveau
Nouveau
User avatar

Joined: 26 Apr 2005 12:00
Posts: 696
Location: PARIS
Bonjour,

Il n'existe pas vraiment d'outil pour simuler une mont?e au plan en 6.1.03.
A moins de d?velopper ? partir du scj?ma de la base un script pour le faire.

N?anmoins je vous pr?coniserai bien une autre solution.
Sans avoir ? modifier vos Control-M Server et Control-M Agents install?s, il pourrait ?tre int?ressant d'updater Control-EM vers une version 6.2.01 ou 6.3.01 avec l'option Control-M Forecast.

Int?grer depuis la version 6.2 vous pouvez re-jouer votre plan avec l'option playback. Forcast quand ? lui permet justement de visualiser une production en simulation int?gralement ou partiellement.


*****************************************************************

Hello,

There really does not exist of tool to simulate a rise in the plan into 6.1.03. Unless developing starting from the database poster a script to do it.

Nevertheless I will recommend you well another solution.
Without having to modify your Control-M Server and Control-M Agents installed, it could be interesting to upgrade Control-EM towards a version 6.2.01 or 6.3.01 with the option Control-M Forecast.

To integrate since version 6.2 you can play again your previous plan with the option playback. Forcast when him precisely allows to visualize a production in simulation completely or partially.


Top
   
PostPosted: 21 Dec 2006 4:12 
Hi,

Go to see following link on that site
Pro-active Workload Planning
It must be give you some other solution to help you.

Regards

JVLJVL


Top
   
Display posts from previous:  Sort by  
Post new topic  Reply to topic  [ 3 posts ] 

All times are UTC+01:00


Who is online

Users browsing this forum: No registered users and 1 guest


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Limited
The site created by Franck YOT. Images, logo, content and trademarks about Control-M products are property of BMC Software.
All the comments are property of their posters. Images, logo, content and design are © copyright by Scheduler-Usage.com. All Rights Reserved