Hi Experts,

I have two jobs:

Job 1 runs from Monday - Friday
Job 2 runs from Sunday - Thursday

Job 2 has a dependency on Job 1 so Job 1 (OUT) Condition going to Job 2 as (IN) condition with ODAT. This setup works fine from Monday till Thursday.

On Sunday Night, when "Job 2" comes to ControlM it waits for "Job 1" OUT condition (for Sunday) but unfortunately "Job 1" finished on Friday so it doesn't get it.

Here are more details : Job 2(date : 08/02) and waits for Job 1 condition for (08/02) but database has "Job 1" condition as 07/31. We need to run "Job 2" on Sunday night with "Job 1" Friday's condition.

If I create replica of "Job 2" and keep it for Sunday night then which date I need to select for "Job 1" condition. PREV will not work here as "Job 2" previous scheduling date was 07/30.

Please provide valuable inputs on this case.

Thanks


Top
   
PostPosted: 10 Aug 2015 7:03 
Offline
Nouveau
Nouveau
User avatar

Joined: 03 Mar 2010 9:00
Posts: 5
Hi DhirajRay.

You can use ctmldnrs to load conditions on Sunday. That utility works in Control-M/Server and let you add conditions.

Regards


Top
   
Display posts from previous:  Sort by  
Post new topic  Reply to topic  [ 2 posts ] 

All times are UTC+10:00


Who is online

Users browsing this forum: Bing [Bot] and 3 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Limited
The site created by Franck YOT. Images, logo, content and trademarks about Control-M products are property of BMC Software.
All the comments are property of their posters. Images, logo, content and design are © copyright by Scheduler-Usage.com. All Rights Reserved