Hello experts,

I need to know how to fill in the scheduling for a new job in Control-M 7.0
This job need to run on the first Monday of the month at 06:00 AM.
I want to use the calendar "Alldays" because I have no rights to make a new calendar, I have no idea if this is possible.
I hope to here something.

Best regards,

Leonard Dronkers


Top
   
 Post subject: Re: Scheduling job
PostPosted: 16 Nov 2014 8:09 
Offline
Nouveau
Nouveau
User avatar

Joined: 21 Mar 2013 9:00
Posts: 11
Location: India
Hi Leo,

In Week Days section, Rules filed <D1W1> and in Calender select "Alldays"cal. (If ur week start with Monday)

D2W1 if ur week start with Sunday.

Also Submit between field 06:00 AM.


Top
   
 Post subject: Re: Scheduling job
PostPosted: 21 Nov 2014 8:30 
Offline
Nouveau
Nouveau
User avatar

Joined: 07 Nov 2011 9:00
Posts: 4
Hi Rocket,

Thanks for your answer, i'm afraid this is not solving my problem. :cry:
It's has to run on monday morning at 06:00am, so the sunday before it needs to be schedule. In fact it is the first monday of the month, and then 1 day back :D

Greetz Leonard.


Top
   
 Post subject: Re: Scheduling job
PostPosted: 24 Nov 2014 11:55 
Offline
Nouveau
Nouveau
User avatar

Joined: 21 Mar 2013 9:00
Posts: 11
Location: India
Hi,

When NDP happens? Also time zone for Agent if any!

We normally consider 00:00 as NDP time.

-Sandeep Kolli


Top
   
 Post subject: Re: Scheduling job
PostPosted: 24 Nov 2014 4:51 
Offline
Nouveau
Nouveau
User avatar

Joined: 07 Nov 2011 9:00
Posts: 4
Hi Sandeep,

Our NDP started at 12:00 pm :)

Greetz Leonard.


Top
   
 Post subject: Re: Scheduling job
PostPosted: 27 Nov 2014 1:10 
Offline
Nouveau
Nouveau
User avatar

Joined: 13 Jun 2007 8:00
Posts: 317
Schedule it exactly as what you have said.

Quote:
In fact it is the first monday of the month, and then 1 day back


Set the job to run at 6am on first Monday of each month. Add confirmation calendar to shift one previous day.


Top
   
 Post subject: Re: Scheduling job
PostPosted: 02 Dec 2014 8:30 
Offline
Nouveau
Nouveau
User avatar

Joined: 07 Nov 2011 9:00
Posts: 4
Perfect, that was it :D

Thank guys for helping me.

Grtz Leonard.


Attachments:
Control-M scheduling.jpg
Control-M scheduling.jpg [ 170.46 KiB | Viewed 3278 times ]
Top
   
Display posts from previous:  Sort by  
Post new topic  Reply to topic  [ 7 posts ] 

All times are UTC+10:00


Who is online

Users browsing this forum: Bing [Bot] and 2 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Limited
The site created by Franck YOT. Images, logo, content and trademarks about Control-M products are property of BMC Software.
All the comments are property of their posters. Images, logo, content and design are © copyright by Scheduler-Usage.com. All Rights Reserved